Finite capacity rough-scheduling


Finite capacity rough-scheduling

Finite capacity rough-scheduling considers and levels load on resources, and calculates the estimated LST.
Finite capacity rough-scheduling uses the time wise load leveling command.

 

Resource wise load leveling command

In case of resource wise load leveling, operations are assigned from due date with backward direction and infinite capacity

Time wise load leveling command

In case of infinite capacity, overlapped operations will be expand along the time axis and will be reduced in the resource axis, but the area of the operation bar is not changed. It means the operation production time is expanded but the resource qty consumed by the operation is reduced.
Material purchase date can be calculated from the operation last start time (LST).

Finite capacity rough-scheduling commands

Finite capacity rough-scheduling parameter command is composed of the followed basic commands.

 

Upload selected orders

 

Filter orders

 

Unassign all

 

Explode orders

 

Assign result constraint operations

 

Assign time fixed operations

 

Resource wise load leveling

 

Time wise load leveling

 


HelpNo.:777700
©2017 Asprova Corporation, All rights reserved.