Reassignment

Steps

Resource Gantt chart

You can reassign orders and operations that are selected on the chart.

Reassigning orders

If you execute [Order] - [Reassign] from the popup menu for orders selected on the chart, the orders will be

unassigned (when the orders are already assigned),

exploded,

scheduled,

and all the operations of the selected orders will be reassigned.

Reassigning operations

If you execute [Operation] - [Reassign] from the popup menu for operations selected on the chart, the operations will be

unassigned (when the orders are already assigned),

scheduled,

and all the selected operations will be reassigned.


In both cases of reassigning orders and operations, the currently selected parameter will not be referred to. Orders and operations will be reassigned according to the following settings.

 Assignment directionNot specified
 Resource selection methodFirst resource found
 Resource quantity constraintsUnspecified
 Forward (Assignment end time)Ignore
 Forward (due date)Ignore
 Backward (Assignment start time)Ignore
 Backward (EST)Ignore

*If you want to specify splitting of operations or items and reflect that setting onto the Gantt chart immediately after specifying, please use the order reassignment feature.

*Since Asprova will select resources on a first-found basis, if you want to assign operations to the resources to which the operations are currently assigned, please fix the resources first and then execute [Reassign].

*Since Asprova will try to assign operations starting from EST (LST if backward scheduling), if you want to assign operations to the positions at which the operations are originally assigned, please fix the assigned time first and then execute [Reassign].