Reschedule selected operations by command execution

Steps

Resource Gantt Chart

Reschedules multiple operations on a chart or table, using the scheduling parameters.


From the resource gantt chart

Select the instructions that you wish to reschedule from the Resource gantt chart and choose the "Execute command" sub-menu from the Resource gantt chart's use instruction popup menu.

From the chart's operation line

Select the operations that you wish to reschedule from the Order gantt chart's operation line, the Operation gantt chart or the Drilldown Operations and choose the "Execute command" sub-menu from the operation bar's popup menu.

From the order gantt chart

Select the "Execute Command" popup menu in order gantt chart. In case that an order is selected, all the operations of this order are be collected.(From Ver.7.2.2).

From the pegged orders gantt chart

Select the "Execute command" sub-menu from the left part right-button popup menu in pegged orders gantt chart. All the operations of selected pegged order are be collected.(From Ver.7.2.2).

From dispatching view

Select the use instruction which you wish to reschedule in dispatching view. Choose the "Execute command" sub-menu from the left part right-button popup menu.

From the operations table

Select the operations that you wish to reschedule from the Operation table and choose the "Execute command" sub-menu from the right-button popup menu.

From order table

Select the operations that you wish to reschedule from the order table. Choose the "Execute command" sub-menu from the left part right-button popup menu. All the operations of selected order are collected.(From Ver.7.2.2)

From use instruction table

Select the operation which you wish to reschedule in use instruction table. Choose the "Execute command" sub-menu from the left part right-button popup menu. The parent operation of selected use instruction is collected. (From Ver.7.2.2)

From the tool bar

Instead of choosing the "Execute command" sub-menu from the popup menu, you can reschedule by clicking on the Tool bar command button.


The tool bar menu supplied as default is as shown below.

 Same item grouping Group the selected operations by item (Item code) and reassign.
 Same Spec1 grouping Group the selected operations by Spec1 and reassign.
 Same Spec2 grouping Group the selected operations by Spec2 and reassign.
 Same Spec3 grouping Group the selected operations by Spec3 and reassign.
 Same Spec4 grouping Group the selected operations by Spec4 and reassign.
 Num Spec1 ascending Reassign the selected operations by Num Spec1 ascending.
 Num Spec1 descending Reassign the selected operations by Num Spec1 descending.
 Num Spec2 ascending Reassign the selected operations by Num Spec2 ascending.
 Num Spec2 descending Reassign the selected operations by Num Spec2 descending.
 Num Spec3 ascending Reassign the selected operations by Num Spec3 ascending.
 Num Spec3 descending Reassign the selected operations by Num Spec3 descending.
 Num Spec4 ascending Reassign the selected operations by Num Spec4 ascending.
 Num Spec4 descending Reassign the selected operations by Num Spec4 descending.
 Due date ascending Reassign the selected operations by the due date of the orders.
 Starting order Reassign selected operations by Starting order. (From Ver.7.2.0)


The scheduling parameter's of the default tool bar menu

Scheduling parameters are connected to the tool bar menu's reassign commands. The reassign scheduling commands have the command structure and properties as shown below.

Command structure

The reassign scheduling commands have the following command structure.



 Upload selected operations (selected by GUI) Gather all the operations selected on the upper-most chart or table.
 Filter operations Filter the gathered operations.
 Unassign all To reassign, first of all temporarily unassign all the operations.
 Assign manufacturing orders Assign the filtered operations.
 Evaluate schedule Evaluate the results of the schedule.

Property setting

The reassign scheduling parameters provided by default are set to assign in order from the left.

The parameters have been set so that the selected operations, for the period of time from the start of the selected operations to the end of the operations are assigned in order from the right.

The main properties are the following.

Dispatching rule

Set the dispatching rule in accordance with each menu. Please see below for more details.

Assignment type

Set to "Finite Capacity" to assign from the left in order using finite capacity.

Assignment direction

Set to "Forced forward" to assign from the left without being dependent on the fixed level.

Resource selection method

Set to "Current resource" to reassign operations that have already been assigned.

Temporary operation fix

Set to "None" because the operations will be reassigned in order from the left.

Production time calculation

Set to the general setting of "Main resource".

Assignment start time

Set to "Min(ME.OperationList,TARGET.StartTime)" to assign forward with the earliest start time of the chosen operations.

Assignment endtime

Set to "Max(ME.OperationList,TARGET.EndTime)+1d" to assign the chosen operations within the range of the latest end time plus one day.

Split operations

Set to "No" to reassign the split operations as they are.

Assign split operations near each other

Set to "No" to individually reassign the split operations according to the dispatching rule.

Dispatching rule absolute

Set to "Yes" to enforce the ordering of the reassignment to be that of the dispatching order, from the left.

Ignore unassigned pegged operations

Set to "Yes" to reassign even when the operations pegged before and after are unassigned.

Filter operations

Set to "(ME.Order.Type=='M')&&(ME.TimeFixedLevel==0)" so that the only operations that will be assigned will be those that are scheduled operations of manufacturing orders (and not result operations, frozen operations, released operations or fixed operations).


In order to display the reassign commands in the popup menu but not display them in the Scheduling parameters combo box set the following properties.

Parameter type

For display in a pop-up menu, set this to “Parameter for reassignment”.

Display in combo box

Set to "No" to not display in Scheduling parameter combo box.

Display order

By setting the display order you change the display order in the popup menu.


The dispatching rule reassign scheduling parameters supplied as standard are as follows.

 Same item grouping Item Code Ascending
Operation production start time Ascending
 Same Spec1 grouping Spec 1 Ascending
Operation production start time Ascending
 Same Spec2 grouping Spec 2 Ascending
Operation production start time Ascending
 Same Spec3 grouping Spec 3 Ascending
Operation production start time Ascending
 Same Spec4 grouping Spec 4 Ascending
Operation production start time Ascending
 Num Spec1 ascending Num spec 1 Ascending
Operation production start time Ascending
 Num Spec1 descending Num spec 1 Descending
Operation production start time Ascending
 Num Spec2 ascending Num spec 2 Ascending
Operation production start time Ascending
 Num Spec2 descending Num spec 2 Descending
Operation production start time Ascending
 Num Spec3 ascending Num spec 3 Ascending
Operation production start time Ascending
 Num Spec3 descending Num spec 3 Descending
Operation production start time Ascending
 Num Spec4 ascending Num spec 4 Ascending
Operation production start time Ascending
 Num Spec4 descending Num spec 4 Descending
Operation production start time Ascending
 Due date ascending Order due date Ascending
Operation production start time Ascending
 Starting order Starting order Ascending


Tool bar command button display

The reassign command buttons are normally not displayed. Please follow the instructions below to display the tool bar.

From the menu bar [Tools]-[Customize...] display the Toolbar Customize dialog and add a new tool button.
From the "Commands" tab in the Toolbar Customize dialog select the "Schedule" category to display the tool buttons for the reassign scheduling parameters supplied as standard.Add the necessary commands to the toolbar.



Create and edit the reassign scheduling parameters

The reassign scheduling parameters can be created in the same way as the usual scheduling parameters by using the Command Editor dialog.

In the Command Editor dialog, under Custom commands, select "Gantt chart bar popup menu" from the drop down list box and click the "New" button.
If you select "Gantt chart bar popup menu" from the drop down list box in Command list your added command will be displayed.

After this you can add commands in the same way as you do for usual scheduling parameters. Orders or operations can be selected by "Upload selected orders" and "Upload selected operations" command in GUI.

 

Orders or operations can be selected by "Upload selected orders" and "Upload selected operations" command in GUI. Then selected orders or operations can be dealt with.

You can also use the Scheduling Parameter table (open from menu [Table View]-[Command]-[Scheduling Parameter]).



Uses other than assign

By arranging the commands it is possible to do things other than assign.

<Example 1>

As shown below, by using the "Modify properties" command you can make a popup menu to change the status of the selected operations.
Double click "Modify property" row in "Scheduling parameter table".
Set the "Operation expression" property ( General tab ) on the dialog as follows to change order status to "B [Completed]". ME.Status=='Completed'


 

<Example 2>

Add a menu to remove the split operation settings that have been set for operations. See here for settings.


<Example 3>

Set the status of selected operation as "Completed".
Double click "Modify property" row in "Scheduling parameter table".
Set the "Order expression" property ( General tab ) on the dialog as follows to change order status to "B [Completed]". ME.Status=='Completed'



HelpNo.:742300