Top Part Popup Menu

Order Gantt chart


The top part popup menu of the order Gantt chart is a popup menu that is displayed by right-clicking the mouse on the top part (date cells of the time chart) of the order Gantt chart.

The top part popup menu provides the following items:

Time Settings

Displays the Time period tab for the project settings in the properties window.

Holiday

Specifies whether to show the day as holiday using holiday width ratio.
When ticked, the width of the day is determined by holiday width ratio.

Unit term

Specifies the unit of time or time period by which you want the columns to be displayed on the time chart.

Display period

Re-display the time chart in the specified period.