Specifying the minimum and maximum quantities a resource can produce at once


Here we will specify the minimum and maximum quantities that a resource can be produced at once.

Steps

  1. For the "Resource split size MAX" of a resource, specify the maximum quantity that the resource can produce at once.
  2. For the "Resource split size MIN" of a resource, specify the minimum quantity that the resource can produce at once.

If you specify zero for both of the resource split size MIN and MAX, there will be no constraint.
If production quantity of an operation is smaller than the resource split size MIN, the operation's production quantity will be increased to the resource split size MIN. (However, the increased quantity cannot be reflected to the input item.)
If the production quantity of an operation is larger than the resource split size MAX, the operation will automatically be split.

Example

Specify that Mixer1 produces in the unit of 20 and Mixer2 produces in the unit of 0 to 30.

[Resource Table]
CodeResource split size MINResource split size MAX
Mixer12020
Mixer2030


Related Topics

Operation Split

Resource Split Size MIN

Resource Split Size MAX