Forcibly setting a setup time to 0 between same items


Here we will specify to forcibly make a setup time 0 if operations which have the same output items are assigned next to each other.

Steps

  1. Click on the [Project Settings] button on the toolbar.
    Or, select [Schedule] - [Project Settings...] from the menu.
    Properties for the project settings appear in the properties window.
  2. Select the [Settings] tab from the properties window.
    Properties for the settings appear in the properties window.
  3. Check the "Zero setup time between same items" property.