Specifying a setup time for changing sub resource


Here we will specify a setup time to occur depending on the combination of sub resources assigned to lefthand and righthand operations.

Steps

  1. In the "Resource" field of the resource setup table, enter a resource that requires a setup.
  2. In the "Resource L" and "Resource R" fields of the resource setup table, enter a combination of resources.
  3. In the "Setup time" field of the resource setup table, enter a setup time in minutes.

Example

MoldingMachine1 requires a setup time of 30 minutes to replace MetalMold1 with MetalMold2.

[Resource Setup Table]
ResourceResource LResource RSetup time
MoldingMachine1MetalMold1MetalMold230