Carrying out split operations in parallel


Here we will assign split operations to multiple resources in parallel.

Steps

  1. Right-click on the operation you want to split and assign in parallel to display a popup menu. Select [Operation] - [Edit Operation...] from the popup menu.
  2. Specify the split setting using the "Split number" or "Split ratio" property in the Split tab.
  3. For the "Split parallel number" property in the "Split" tab, specify the number of resources to which you want to assign the split operations.
  4. If you reschedule, the operation will be split and assigned according to the split number and split parallel number you specified.


HelpNo.:116000