Starting point in the time relationship between current and previous processes

Asprova APS Introductory Manual

Back

Next

Let's Start Asprova APS


While the time relationship between current and previous processes is defined by the time constraint method, time constraint MIN (MAX), and resource time buffer, the starting point (i.e., whether the starting point will be the production task or setup task) differs depending on which of the setup / production / teardown properties for the input instruction and the output instruction you specify values for.

(1) Defining a relationship between the production of the previous process with the production of the current process (default relationship)

<Output instruction of the previous process>
SetupProductionTeardown
BlankBlankBlank

<Input instruction of the current process>
SetupProductionTeardown
BlankSpecify here the required quantity (Default value is 1.) Blank

(2) Associating the teardown of the previous process with the production of the current process

<Output instruction of the previous process>
SetupProductionTeardown
BlankBlank1

<Input instruction of the current process>
SetupProductionTeardown
BlankSpecify here the required quantity (Default value is 1.) Blank

(3) Associating the production of the previous process with the setup of the current process

<Output instruction of the previous process>
SetupProductionTeardown
BlankBlankBlank

<Input instruction of the current process>
SetupProductionTeardown
Specify here the required quantity. (Setting is required even when the value is 1.)BlankBlank

(4) Associating the teardown of the previous process with the setup of the current process

<Output instruction of the previous process>
SetupProductionTeardown
BlankBlank1

<Input instruction of the current process>
SetupProductionTeardown
Specify here the required quantity. (Setting is required even when the value is 1.)BlankBlank